Dunaferr’s
Coking Battery No. 3 is working with its full capacity again.
By the implementation of the whole investment the 65 chambers
of Coking Battery No. 3 which were reconstructed in two phases
provides the production of 830-850 thousand tons of dry quenched
coke annually. The amount produced by this way can cover
the total furnace-coke supply of DUNAFERR Zrt.’s blast furnaces. By
this Dunaferr made great strides towards coke production providing
a long term condition of integrated steel production. The total
amount of coke that can be produced in Coking Batteries No.
1 and 3 may exceed 1 million tons according to the total capacity
before 2000.
Reconstruction works of Dunaferr’s Coking Battery No. 3 started
in 2002. First a decision was made to reconstruct the battery part
being in worse condition – 33 chambers. The investment amounting
totally to HUF 3.6 billion finished in May, 2003. Even in that
September an agreement was concluded about the reconstruction of
the battery part containing 32 chambers. As the first step of the
works of the second phase the battery part was stopped, the disassembly
of the refractory walls and the mechanical equipments were carried
out and in order to protect the state of the remaining parts a
covered store was built. Following these the adequate renovation
of the regenerator zone was carried out in several phases.
Following the closing of Dunaferr’s privatization process reconstruction
works speeded up and in January, 2005 a main contractor’s contract
for finishing the reconstruction was concluded between DUNAFERR
and the Ukrainian Azovimpex Ltd. belonging to the interests of
the Industrial Union of Donbass. Refractory walls as well as the
mechanical equipments of the Coking Battery were renovated, while
in the implementation of other works in connection with reconstruction
(e.g. renovation of furnace machines, logistic tasks) have been
carried out by companies belonging to Dunaferr Company Group and
other Hungarian ventures – mainly from Dunaújváros.
As an important step of the reconstruction works drying and heating
of the walls of the reconstructed battery part started last December.
Besides these works mechanical assembly is continuing and due to
preliminary assumptions the running up of the total capacity may
be carried out in March, 2006.
Reconstruction of the battery part renovated in the second phase
and the mutual cost of the related tasks was approximately HUF 4.1
billion, so the total investment at the coking battery amounts to
some HUF 7.7 billion together with the battery part renovated in
2003.
|